100,000 feet installed in Phase One construction
1:02AM October 22, 2017
We have installed nearly 100,000 feet of strand, which the fiber will be attached, to power poles in and around Miner, Mo. We have poured concrete pads for fiber buildings at two substations. On Monday, the backup generator for the network operations center – The Hut – will be put in-service at Sikeston. We expect to announce the full lineup of services in the coming weeks and anticipate connecting some Miner-area homes in late January.