Pad poured, five miles of strand pulled in Miner
8:18AM September 28, 2017
For our member-owners in the Miner area, progress continues on our first phase to provide fiber internet within the next four months. More than five miles of 23 total miles of strand has been pulled. Once we pull the strand, crews will come back and attach the fiber. Plus, the concrete pad for Miner’s fiber hut, which allows connectivity to SEMO’s other substations, to our Sikeston HQ and to our regional and national broadband partners, was poured today.