Inside the Fiber Warehouse
10:17PM February 05, 2018
Here’s a behind the scenes look at the fiber warehouse for our gosemofiber.com project. So far, more than 250,000 feet of fiber and 240 of ~450 taps (provides fiber connectivity to homes) have been installed for the first construction phase in Miner. It takes about two hours to prep, install and slice each tap. It appears we are in the top of the eighth inning as we build the fiber Gig network from the ground up. Thank you for the patience and support. Thanks to Ervin Cable Construction for the partnership.